  • Statement Showing progress of Execution of the projects under Infrastructure Development Scheme as on 20.10.2022
    Sl. No Name of District Name of Town Name of Projects for which DPRs are prepared Total project cost in lakhs A.A No & date Physical progress Fund Releasesd 2021-22
          IDS projects at jagiroad Urban Area Revised AA For Rs.1877.1400 AA/TCP_2021-22(I)_270 31.03.2022   Letter No.- & date Amount
    1 Nagaon Jagiroad      
    I (I) Part-(I) Development of Water Front at jagiroad 957.48 30%    
    II (II) part -II costruction of Multi-Utiliy Building at jagoroad 198.95 80% No.FS/TCP_2021-22(I)_92, dated 05.01.2022 73.05758
    III (III) part-III costruction of Multipurpose Auditorium at jagiroad 720.71 60% No.FS/TCP_2021-22(I)_56, dated 09.11.2021 145.60077
    2   Lunghin costruction of Market Complex at Lunghin town  70.07348 No.AA/TCP_2020-21(I)_206 17.02.2021 60% No.FS/TCP_2021-22(I)_184, dated25.02.2022 40.00
    3   Mahur costruction of fish market at Mahur town  69.47 No.AA/TCP_2020-21(I)_200 06.02.2021      
    4 Nagaon Nagaon Development of Kachulukhowa rash Field at Nagaon 77.99 No.AA/TCP_2020-21(I)_204 09.02.2021      
    5   Donkamukam Improvement of Road woks at Donkamukam  100.00 No.AA/TCP_2020-21(I)_205,  12.02.2021 100% No.FS/TCP_2021-22(I)_212, dated 05.03.2022 99.98702
          TOTAL 2194.67348         358.64537